The Process Begins Phase A Studies to Look at I-27 Route in Northeastern New Mexico

By Marty Mayfield

KRTN Multi-Media

Terry Doyle, Parametrix Vice President, was on hand at the Raton High School Monday evening November 16, 2026, where about 30 plus residents showed up provide input to begin the study process after the federal government designated US 64/87 as I-27, a part of an ever-growing interstate system to improve transportation and commerce movement north and south as part of the Ports to Plains Corridor.

Doyle noted in his presentation that there is no funding for I-27 construction in New Mexico at this time and that depending on funding and collaboration with other agencies the full development process could take up to 20 plus years. The $1 million dollar check that Congress Woman Teresa Ledger Fernandez presented in Raton is helping to pay for this study.

The Ports to Plains corridor was first proposed in 1998 and further defined in 2000 and 2001. With that designation it wasn’t long before the widening project of US 64/87 to four lanes was underway. US 87 is now four laned from Dumas Texas to Raton with the exception of the 24-mile stretch between Dumas and Hartley. That stretch of road is currently under construction with dirt work to be completed this fall and winter and paving to begin in the spring.

As the study process begins the study will identify areas that need to be improved to meet interstate standards and evaluate current and future needs. The study will also assess corridor conditions and constraints as well as evaluate potential I-27 alignments along with interchange locations and frontage road options. Parametrix will also look at local access and community connectivity needs as identifying potential right of way considerations. Other considerations include environmental resources, sensitive areas within the corridor and to gather stakeholder and community feedback.

Currently the US 64/87 is a four laned divided highway with multiple access points along the highway allowing access to county and ranch roads. An interstate highway has limited access with access to the highway at interchanges and access to county and ranch roads via frontage roads. While the four-lane highway right of way may only be up to 200 feet wide the Interstate right of way can be as much as 300 to 400 feet including frontage roads. This additional width could require realignment of the current roadway structure.

Parametrix surveyors were out along the current highway collecting existing data on the highway. The study now engages the public and stakeholders to gather information on access and other concerns along the route. Throughout the study Parametrix will continue to engage the public and by the summer of 2027 will have a draft of Phase 1A ready for presentation.

The first question asked in the Q&A portion of the meeting was where will the interchange with I-25 be located? Doyle told the crowd that it could be from the current location to south of Raton near the three-mile interchange. Other concerns included the width of the right of way as well as wildlife interactions along the route. Ponds and low-lying areas that collect water and how will those areas will be handled in the design.

Economics will be looked at extensively during the work and Doyle noted that studies have shown that counties with an interstate through them have a higher GDP that those that don’t. Another question asked was how can Raton future proof depending on where the interchange is actually placed? Doyle noted it will be a big part of the conversation both in where the interchange is placed and future proofing. They will be looking at intelligent transportation systems in the process to help with the design.

Colfax County Commissioner Si Trujillo asked about the alignment around Capulin and Des Moines as many of his constituents rely on and have connections to those communities. Doyle noted that too is one of his concerns and he is hoping to get more on that as they have their meeting in Des Moines. As much of the route is through prime cattle country Doyle is hoping to hear more from ranchers about the route to be more of a benefit rather than a hindrance.  He noted that there needs to be more conversation about the project so that they get it right.

Contact information and how to provide your two cents.

map of the Parametrix study area through northeastern NM
Some of the benefits that the interstate should bring to the area
Ports to Plains history timeline
some of the goals of the I-27 study process.
The differences between the existing four lane highway and how an interstate highway is designed.
Study phase timeline.