ATTENTION SPRINGER ELECTRIC COOP MEMBERS IN RATON, FOLSOM AND THE SURROUNDING AREAS:
Springer Electric Coop will be running new transmission and distribution lines into the new Raton substation and will need to take an outage. This work is scheduled for Monday, March 24 from approximately 9 am to 3 pm.
We apologize for any inconvenience and appreciate your patience while this necessary work is completed.
If you have any questions, please call Springer Electric Coop office at 575-483-2421.
ATTENTION RATON PUBLIC SERVICE CUSTOMERS
Springer Electric Coop has requested a 2-hour power outage for the Raton Public Service customers on Monday March 24, 2025, from 9:00am to 11:00am.
This system-wide outage is for the new Springer Electric substation on Gardner Road that ties to the Raton transmission line. The emergency transmission tie to the South will be unavailable for approximately 10 – 14 days.
There will also be another 2-hour power outage in the near future to complete the tie
to the South transmission line. Raton Public Service will put the notice out as soon as
possible.
Raton Public Service asks you to prepare for this scheduled outage.
David W Piancino
General Manager
Raton Public Service